Skip to main content

Côte d’Ivoire: Construction of the country’s largest gold mine to begin soon

This page was translated from French with the assistance of artificial intelligence, using the portal's economic glossary. The French original prevails in case of doubt. View the French original

At the Council of Ministers meeting on 10 July 2024, the government of Côte d’Ivoire adopted two decrees granting operating permits for a gold deposit in the departments of Dianra and Kani. In addition to becoming Côte d’Ivoire’s largest gold mine, this major project will rank as the third-largest gold project in West Africa.

The Koné project stands out as a flagship of Côte d’Ivoire’s gold industry, with total production expected to exceed 100 tonnes of gold over a period of 16 years. The Canadian mining company Montage Gold, which owns the project, is continuing its exploration efforts to increase estimated reserves and optimise the future output of this first-rate gold mine.

By the end of the first half of 2024, Montage Gold had completed a total of 21 175 metres of drilling at the site as part of an ambitious campaign to strengthen the Koné project’s resources before operations begin. With a budget of 6 million dollars for 30 000 metres of drilling, the programme is expected to be completed in late July 2024. A second drilling programme, covering an additional 60 000 metres, will be launched at the end of the third quarter, targeting new mineral resources. This initiative could lead to a significant increase in production forecasts and revenue generated by the future gold mine.

According to a feasibility study published in January 2024, the Koné project could produce an average of 223 000 ounces of gold annually over a period of 16 years, with an annual peak of 378 000 ounces, for total production of 3,57 million ounces (approximately 101 tonnes of gold). The initial investment required to deliver the project is estimated at 712 million dollars, with the mine expected to enter service in 2027. The Koné project will thus add to Côte d’Ivoire’s recent significant contributions to gold production, including the Abujar and Séguéla mines in 2023 and the Lafigué mine since June 2024.

The construction phase is expected to generate approximately 2 500 direct jobs, and the production phase will create an additional 1 000. Montage Gold has also undertaken to invest 19,8 billion CFA francs (FCFA) in local development. The permits granted have a combined validity period of 28 years, with the possibility of extension in the event of new discoveries.

It should be noted that gold production in Côte d’Ivoire is growing steadily, rising from 51 tonnes in 2023 to a forecast 55 tonnes in 2024. With its extensive reserves and production potential, the Koné project represents a major step forward in increasing national gold output, thereby strengthening Côte d’Ivoire’s economic momentum and sustainable development.

Source : Agence Ecofin, MEPD Web Portal Editorial Team