The Ivorian economy recorded strong momentum, with average real GDP growth of 5,5% over the 2019-2023 period, driven by substantial public and private investment. In nominal terms, these investments rose from 7 845,9 billion CFA francs (FCFA) in 2019 to 11 175,9 billion FCFA in 2023.

Source : MEF/DGE/, INS

 

The country's current development policy is set out in the National Development Plan (PND) 2021-2025, valued at 59 000 billion FCFA. The expected contribution of the private sector amounts to 43 646,7 billion FCFA, or 74% of the total. Several major projects are planned for implementation with the participation of the private sector. For more information :www.gcpnd.gouv.ci

 

 

Source: MEPD/DGE

Trend in FDI according to CEPICI data in Côte d’Ivoire in 2024

In 2024, foreign direct investment (FDI) recorded in Côte d’Ivoire declined slightly compared with the previous year. Total FDI volume fell from 436 billion FCFA in 2024, compared with 471 billion FCFA in 2023, a decrease of 7,4 %. This decline may be linked to a global economic slowdown as well as strategic adjustments by international investors.

Despite this overall decline, some sectors continued to attract foreign capital, while others recorded a marked fall. The agri-food/agro-industry sector accounted for (38,91%) of investment, followed by telecommunications (20,73%) and other manufacturing industries (10,63%).

The leading investor countries were Mauritius (30,47%), France (12,99%), Singapore (11,20%) and China (5%).

Approved Investments, 2012-2024

Investment approval

Categories

2012

2013

2014

2015

2016

2017

2018

2019

2020

2021

2022

2023

2024

TOTAL

Investment volume (in billions of FCFA)

219

514

426

670

672

466

703

730

632

642

714

471

436

7295

FDI (in billions of FCFA)

119

380

261

423

491

373

544

553

338

357

496

471

436

5242

IDN (in billions of FCFA)

100

134

165

247

181

93

159

177

294

285

218

0

0

2053

Source : CEPICI

Source : CEPICI

 

  • Breakdown of FDI by sector of activity

The table below shows the main sectors of activity that attracted the most FDI. These are: (i) agri-food/agro-industry, 169 billion FCFA (38,91%); (ii) telecommunications, 90,35 billion FCFA (20,73%); (iii) other manufacturing industries, 46,33 billion FCFA (10,63%); and (iv) the chemical industry (cosmetics, pharmaceuticals and rubber), 44,95 billion FCFA (10,32%).

However, investment trends were more mixed in sectors such as other services, 4,73 billion FCFA (1,09%); petroleum products, 1,51 billion FCFA (0,36%); education/training/health, 701 million FCFA (0,16%); and food-crop farming and livestock, 428 million FCFA (0,10%).

 

Breakdown of FDI by sector of activity (in billions of FCFA), 2024

Sector of activityFDI amountPercentage
AGRI-FOOD / AGRO-INDUSTRY

169 604 529 451

38,91

TELECOMMUNICATIONS

90 351 987 822

20,73

OTHER MANUFACTURING INDUSTRIES

46 335 975 704

10,63

CHEMICAL INDUSTRY (COSMETICS - PHARMACEUTICALS - RUBBER

44 956 660 363

10,32

ENERGY (GAS - WATER)

21 338 217 347

4,90

HOTELS (FOOD SERVICE - ACCOMMODATION)

17 459 533 289

4,01

TRANSPORT / STORAGE (HANDLING)

13 052 561 549

2,99

FOOD-CROP FARMING, LIVESTOCK

11 306 398 772

2,59

CONSTRUCTION

7 234 494 444

1,66

EXTRACTIVE INDUSTRY

6 818 618 939

1,56

OTHER SERVICES

4 731 773 954

1,09

PETROLEUM PRODUCTS

1 516 388 226

0,35

EDUCATION / TRAINING / HEALTH

701 103 381

0,16

EXPORT AGRICULTURE

428 032 641

0,10

Total

435 836 275 882

100

Source : CEPICI

 

 

Change in FDI by sector of activity (in billions of FCFA), 2023 to 2024

  • Origin of FDI by country of origin 

    Sector of activity

    Investment amount

    in FCFA in 2023

    Investment amount in FCFA in 2024Change in %
    AGRI-FOOD / AGRO-INDUSTRY

    150 652 351 671

    169 604 529 451

    12,58

    TELECOMMUNICATIONS

    43 982 505 664

    90 351 987 822

    105,43

    OTHER MANUFACTURING INDUSTRIES

    50 103 828 928

    46 335 975 704

    -7,52

    CHEMICAL INDUSTRY (COSMETICS - PHARMACEUTICALS - RUBBER

    58 910 493 412

    44 956 660 363

    -23,69

    ENERGY (GAS - WATER)

    16 047 696 298

    21 338 217 347

    32,97

    HOTELS (FOOD SERVICE - ACCOMMODATION)

    4 744 631 242

    17 459 533 289

    267,99

    TRANSPORT / STORAGE (HANDLING)

    76 357 219 815

    13 052 561 549

    -82,91

    FOOD-CROP FARMING, LIVESTOCK

    -411 307 602

    11 306 398 772

    2848,89

    CONSTRUCTION INDUSTRY

    38 731 553 368

    7 234 494 444

    -81,32

    EXTRACTIVE INDUSTRY

    11 437 505 549

    6 818 618 939

    -40,38

    OTHER SERVICES

    19 327 735 417

    4 731 773 954

    -75,52

    PETROLEUM PRODUCTS

    -

    1 516 388 226

    -

    EDUCATION / TRAINING / HEALTH

    1 027 162 026

    701 103 381

    -31,74

    EXPORT AGRICULTURE

    -

    428 032 641

    -

    Total

    470 911 375 788

    435 836 275 882

     

 

In 2024, according to CEPICI data, FDI amounted to 435,83 billion FCFA. The table below shows that Mauritius ranked first, with 132,83 billion FCFA, followed by France in second place with 53,16 billion FCFA; Singapore ranked third with 52,77 billion FCFA.

 In Africa, Morocco ranked first with 32,28 billion FCFA, followed by Mali with 22,83 billion FCFA, Burkina Faso with 4,82 billion FCFA and Senegal with 4,63 billion FCFA. They were followed by Tunisia with 3,90 billion FCFA, Guinea with 988 million FCFA, Niger with 920 million FCFA, Mauritania with 853 million FCFA, Togo with 590 million FCFA, Ghana with 27 million FCFA and, finally, Cameroon with 9,55 million FCFA.

 

Main foreign investor countries

RANKORIGIN

INVESTMENT AMOUNT

(in billions of FCFA)

1MAURITIUS132 834 628 030
2FRANCE53 166 666 697
3SINGAPORE52 774 523 207
4UNITED KINGDOM32 884 466 558
5MOROCCO32 282 603 809
6INDIA27 450 497 821
7MALI22 837 863 609
8SWITZERLAND10 815 995 174
9CHINA10 310 823 667
10LEBANON9 547 576 508
11CYPRUS9 354 280 923
12HONG KONG7 174 769 187
13CANADA5 549 260 236
14BURKINA FASO4 824 028 876
15SENEGAL4 636 833 526
16NETHERLANDS4 207 739 497
17TUNISIA3 904 752 921
18UNITED ARAB EMIRATES2 256 099 205
19RUSSIA1 819 125 000
20GERMANY1 301 338 439
21USA1 246 787 707
22GUINEA988 487 138
23NIGER920 212 500
24MAURITANIA853 133 125
25TOGO590 344 968
26ITALY484 316 817
27BELGIUM378 370 551
28TURKEY203 222 375
29MALAYSIA133 545 380
30EGYPT67 500 000
31GHANA27 040 250
32CAMEROON9 559 495
33MONACO-11 731
34CAYMAN ISLANDS-105 582
Grand total435 836 275 883

Source : CEPICI

The top 10 foreign investor countries/strong>

 

 

Source : CEPICI

 

CEPICI's main results for businesses created and jobs projected in 2024

  • Number of businesses created through FDI

Number of businesses created by CEPICI in 2024

CategoriesJanuary-December 2024
Number of businesses created

25 477

Number of jobs projected

by businesses created

4 310

Average time to set up a business

4,3

 

Source : CEPICI

 

Number of businesses approved by CEPICI in 2024

CategoriesJanuary-December 2024
Number of businesses approved

146

Number of jobs planned

per approved business

4 823

Source : CEPICI

 

GUFE in figures

Item20232024Change
Number of applications submitted

NP

NP

NP

Number of companies created

25 429

25 477

0,19% 

Projected number of jobs

5 207

4 823

-7,37% 

Average number of companies created per day

101

 

 

Average time to set up a company, in days

5,2 days

4,3 days

 

Source : CEPICI

 

Sectoral and geographical concentration

  • Analysis of sectors favoured by investors

In 2024, Côte d’Ivoire continued to offer investors a diverse range of attractive sectors, each presenting significant opportunities in light of current economic trends and the priorities of the development plan (PND 2021-2025).

According to CEPICI data, several key sectors attract significant FDI flows. The sectors favoured by investors are as follows :

  • Agro-industry: 169 billion FCFA in investment, with strong potential in the production of cocoa, coffee, cashew nuts and palm oil. Investment in agricultural processing, agri-food and innovative agricultural technologies was particularly attractive ;

  • Information and communication technologies (ICT; TIC) : 90 billion FCFA in investment. This sector is expanding rapidly, with increased Internet access and growing adoption of digital technologies (including software development and digital start-ups) ;

  • Manufacturing industry : 46 billion FCFA in investment. The country is encouraging local processing of raw materials, particularly in agro-industry, textiles and chemicals ;

  • Chemical industry : 44 billion FCFA in investment. The Government has implemented measures and other reforms to improve the sector's productivity and competitiveness ;

  • Energy (gas and water) : 21 billion FCFA in investment. Côte d'Ivoire is seeking to diversify its energy mix by investing in renewable energy, particularly solar and hydropower (construction of solar power plants at Boundiali (37,5 MWc) and Sokhoro (52 MW)). In the gas sub-sector, investments are planned, including stepped-up promotion of blocks and exploration activities to discover new crude oil and natural gas reserves; development of the CI-27 field; and preparation for phase 4 drilling to develop the Espoir field in block CI-26 ;

  • Tourism (food service and accommodation) : 17 billion FCFA in investment. This sector has received increased attention, notably with the organisation of the 2023 Africa Cup of Nations. The State has also launched a major development project for the sector through the « Sublime CI » project, which highlights the country's assets to attract more investors ;

  • Transport and storage : 13 billion FCFA in investment. As an important pillar of the country's economy, the sector has many advantages that open up numerous investment opportunities.

  • Some regions with strong potential

The Sud-Comoé Region is part of the area covered by Agro-pole 3, the food-crop basin and agro-industrial zone near Abidjan. This region offers investment opportunities in several sectors :

  • Grand-Bassam Free Zone : Village of Information Technology and Biotechnology (VITIB) ;

  • Agriculture and agro-industry : establishment of processing plants for cash crops (cocoa, coffee, oil palm and rubber) and development of the fisheries value chain ;

  • Agro-industry : establishment of rubber and oil palm plantations, and processing of oil-palm shell waste and empty coconut shells into by-products ;

  • Mineral resources : The region has gold mining potential and exploration permits, particularly in the departments of Aboisso and Tiapoum.

Agneby-Tiassa is part of the area covered by Agro-pole 5, the food-crop basin and agro-industrial zone near Abidjan. Investment opportunities include :

  • Agriculture: investment in agricultural development, including lowland areas; development of food-crop value chains (rice, market gardening and cassava), cash-crop value chains (rubber, oil palm and cocoa), and livestock and fisheries value chains (fishing and poultry).

  • Agro-industry : processing of agricultural raw materials ;

  • Mining : manganese (Aboudé in the Sub-prefecture of Oress-Krobou) and gold (Taabo and Tiassalé) ;

  • Tourism : ecotourism through the rehabilitation and maintenance of parks and reserves.

The Grand-Lac Region, Yamoussoukro, is part of the area covered by Agro-pole 4, the « Academic and Processing Hub ». The opportunities available are as follows :

  • Agriculture and agro-industry : the launch of the Agro-Industrial Hub in the Bélier Region (2PAI-BELIER) supports the establishment of a foundation for processing and agricultural modernisation by restoring and developing productive capital, modernising land-preparation and communication tools (TIC), and promoting the private sector and industrialisation.

  • Urban sanitation: construction of a modern landfill with electricity generation ;

  • Tourism : rehabilitation of the Abokouamékro wildlife park ;

  • Health : construction of a paediatric hospital ;

  • Mineral resources : the region has gold mining potential ;

  • Transport : construction of a bus station.

The PORO Region is part of the area covered by Agro-pole 1, a processing and export hub for fruit and cashew nuts. Opportunities include :

  • Agriculture: investment in hydro-agricultural development, irrigation infrastructure, and production and storage support; development of food-crop value chains (maize, millet, sorghum, rice and onions), cash-crop value chains (cotton, cashew nuts and mangoes), and livestock value chains (cattle and sheep).

  • Education and training : establishment and operation of schools, middle schools, high schools, and higher education, technical and vocational institutions ;

  • Agro-industry : establishment of industries to process agricultural raw materials (cotton, cashew nuts, mangoes, etc.) ;

  • Tourism : investment in hotel complexes and the creation of tourist routes ;

  • Mineral resources : exploration and development of mineral resources (gold, manganese and tantalum).

The Gbêkê Region is part of the area covered by Agro-pole 4, the « Academic and Processing Hub ». The region offers opportunities in sectors such as :

  • Agriculture : establishment of agro-pastoral farms or financing of agricultural projects; investment in the development of food-crop value chains (yam, rice and cassava) and cash-crop value chains (cocoa, coffee and cashew nuts).

  • Agro-industry : investment in infrastructure for processing agricultural products (cashew nuts and cotton) ;

  • Construction and public works : construction of housing (mid-range, affordable and social housing) ;

  • National education : establishment of schools (construction and operation).

The Grands-Ponts Region is part of the area covered by Agro-pole 5, the food-crop basin and agro-industrial zone near Abidjan. It offers opportunities in :

  • Agriculture: investment in the development of food-crop value chains (market gardening and cassava), cash-crop value chains (rubber and oil palm), livestock and fisheries value chains (fishing and poultry), as well as soilless cultivation.

  • Tourism : construction of beachfront hotel facilities to develop tourism, and beach development ;

  • Fishing : projects to build jetties to revive maritime and fishing activities, establish a wholesale fish market in Jacqueville, and create shrimp and lobster production units ;

  • Oil and gas : project to convert natural gas into ammonia and nitrogen fertiliser ;

  • Construction and public works (BTP) : project to build a new town in Jacqueville over an area of 300 ha.

The geographical distribution of investment in Côte d'Ivoire reflects the country's commitment to promoting economic diversity and the specific opportunities offered by each region.

 

Project catalogue

No.SECTOR : AGRO-INDUSTRY
1Industrial irrigated maize plantation covering 600 Ha
2Industrial chilli pepper plantation covering 50 Ha
3Industrial plantain plantation covering 100 Ha
4Industrial pineapple production over 2000 Ha
5Construction of a cashew nut processing plant with a capacity of 15 000 tonnes per year
6Natural rubber plant processing latex with a capacity of 70 000 tonnes per year
7Shea nut processing plant with a capacity of 1000 tonnes per year
8Construction of a mango and vegetable drying plant (4 000 tonnes of vegetables and 3 000 tonnes of dried mangoes per year) – 2PAI-NORD (CI)
9Construction of a peanut oil and paste plant producing 5 800 tonnes of products per year (1 500 tonnes of oil and 4 300 tonnes of peanut paste per year) – 2PAI-NORD (CI)
10Construction of a plant producing cottonseed oil and animal feed (3 800 tonnes of oil and 10 700 tonnes of animal feed per year) – 2PAI-NORD (CI)
 11Construction of a meat production plant with a capacity of 13 300 tonnes per year – 2PAI-NORD (CI)
12Construction of a mango and cashew apple juice plant (90 000 tonnes of fresh mangoes and 800 000 tonnes of cashew apples processed per year) - 2PAI-NORD (CI)
13Construction of a plant producing oil from shea butter (1 000 tonnes per year) – 2PAI-NORD (CI)
14Construction of a maize flour plant with a capacity of 90 000 tonnes per year – 2PAI-NORD (CI)
15Construction of a packaging plant for fresh market-garden produce (54 000 tonnes of fresh vegetables per year) – 2PAI-NORD (CI)
16Frozen plantain and yam chips production unit with a capacity of 10 000 tonnes per year
17Fruit and vegetable processing unit producing jam, cosmetic products and spices, with a capacity of 18 000 tonnes per year
18Construction of 15 independent cassava processing units, each with a capacity of 25 tonnes per day
19Cassava processing unit with a capacity of 1,5 tonne per day
20Cassava plantation combined with a cassava-to-starch processing plant with a capacity of 12 tonnes per hour
21Okra processing unit with a capacity of 1 tonne per day
22Value addition to products in the cocoa value chain by « Maison Mandjou ».
23Establishment of a 6000 Ha rice-growing complex in central Côte d’Ivoire 
24Development of rice-growing complexes in the Agneby-Tiassa Region
25Establishment of a unit to process raw cocoa beans into finished and semi-finished products (cocoa liquor, cocoa powder, cake and cocoa butter), with a capacity of 30 000 tonnes per year
26Industrial maize plantation covering 100 Ha
27Establishment of an integrated agro-industrial pineapple production and processing unit over 250 hectares
28Establishment of an integrated agro-industrial rice production and processing unit
29Establishment of a unit producing refined oil (olein), stearin and fatty acids (olein/cooking oil: 80 000 t / year, fatty acids: 5 000 t / year; stearin: 20 000 t / year)
30Establishment of a unit producing oil, meal and shells from palm kernels (palm kernel oil / year: 4 000 t / year; meal: 5 000 t / year; palm kernel shells: 12 000 t / year)
31Establishment of a cocoa bean processing unit producing cocoa mass, with a capacity of 3 000 tonnes per year (for cooperatives)
32Establishment of a palm fruit processing unit producing red palm oil, with a capacity of 32 400 tonnes per year
33Establishment of a TSR10-type rubber production plant with a capacity of 12 500 tonnes per year
34Establishment of a natural rubber plant processing latex with a capacity of 33 000 tonnes per year
35Establishment of modern food-crop storage and drying units
36Establishment of three (03) cassava-to-starch flour processing units for the agri-food industry, each with a capacity of 3 000 tonnes per year
37Establishment of a palm oil production unit with a capacity of 6 000 tonnes per year
38Establishment of a modern agro-industrial processing unit for cereals, food crops, tubers and oilseeds, with a capacity of 10 000 tonnes per year 
39Project to take over a semi-industrial unit producing and marketing attiéké and by-products (4,5 tonnes of attiéké /month, 1 tonne of starch, 1 tonne of cassava peel for livestock feed)
40Establishment of a small-scale organic fertiliser plant using cocoa residues, with a capacity of 1 500 tonnes per year
41Establishment of an industrial coconut plantation and processing into by-products
42Establishment of a local coffee processing unit (to be certified) 
43Establishment of an industrial plantation of premium local pepper (to be certified)
44Establishment of an industrial food-crop and fruit plantation (papaya, passion fruit, mangosteen, etc.)
45Project to take over the industrial dessert banana plantation (former CANAVESE) in Akressi
46Establishment of a maize and cassava processing unit in Aboisso 
47Establishment of small-scale cashew processing units
48Development and rehabilitation of irrigated food-crop areas in NAFOUN and DIKODOUGOU
49Establishment of a two-hectare greenhouse market-gardening plantation in Maféré
50Establishment of a four-hectare irrigated plantain plantation in Maféré
51Industrial production of Maféré Bread
No.SECTOR : LIVESTOCK
1Establishment of a poultry farm with 1,2 million birds
2Construction of a modern poultry slaughterhouse with a capacity of 50 000 birds per day
3Development of an integrated cattle ranching project, including a vocational training centre and a fodder production unit (three ranches to fatten 3 000 animals over 1 500 ha)
4Construction of a livestock feed plant using rice bran, mango peel and cashew apple peel (340 000 tonnes of livestock feed per year) – 2PAI-NORD (CI)
5TAABO fisheries park covering 76 Ha
6Fish farming in floating cages with a capacity of 20 000 m3
7Fish feed production plant with a capacity of 2000 tonnes per year
810 modern fish-drying ovens with a capacity of 100 tonnes per day
9Integrated poultry hub covering 16 Ha
10Hatcheries for day-old chicks, with a capacity of 2 300 000 day-old chicks per year
11Pig farm with a capacity of 236 000 Kg per year
12Integrated pig production project
13Organic pig feed production plant with a capacity of 800 tonnes per year
14Construction of a poultry complex to produce poultry and by-products (protein meal)
15Construction of a fisheries production and processing complex in Grand Bassam
16Establishment of a poultry feed production unit with a capacity of 5 000 tonnes per year
17Establishment and operation of a fish farm covering 25 hectares
18Establishment and operation of a marine fishing unit producing 720 tonnes of fish per year
19Establishment of a day-old chick production unit with a capacity of 12 000 000 chicks per year
20Shrimp farming project with annual production of 1200 T
21Aquaculture industry modernisation project on Lake Ayamé
22Fish farming development project (Emeraude Pisciculture Sud Comoé farm): production of 10 tonnes of fresh tilapia per year
23Installation of livestock feed (fodder) production units: 5 000 tonnes per year
24Establishment of a fish farm in LOKOLI
25Support for young people to take up beekeeping and honey production for export in the LOKOLI area
26Construction of a modern abattoir in Maféré
No.SECTORS : LOGISTICS / TRADE
1Development of a logistics platform in the 1000-hectare industrial zone in Bouaké
2Installation of a cold chain with a containerised central refrigeration system
3Construction of the Bouaké wholesale market over 12,4 Ha
4Construction of a space for 200 restaurants / refreshment stands
5Establishment of cold-storage and ripening warehouses (cold chain, particularly for storing mangoes, with a cooling capacity of 80 000 tonnes per year) in KORHOGO
6Establishment of an agro-industrial, commercial and logistics platform (PK 108)
7Construction of terminals and logistics platforms
8Construction of a wholesale market
9Construction of a modern market with a modern shopping centre.
10Establishment and development of industrial zones in Adiaké and Tiapoum
11Construction of themed markets (timber, hardware, mechanics, fisheries products)
12Expansion of the industrial activity zone park in KORHOGO
No.SECTORS : SERVICES / EDUCATION
1Listening and telephone call centre
2Primary and secondary school construction project
3Opening of an international high school (French or American)
4Construction of a municipal plant nursery in Bouaké
5Construction of a cinema and performance venue in Bouaké
6Establishment of a sanitation brigade
7Rehabilitation of the Bouaké municipal swimming pool
8Modernisation of the Waraniéné craft centre
9Construction of an agricultural training centre
10Construction of a vocational high school in the fields of fishing, mining, construction, solar energy, etc. in the region
11Construction and equipping of a girls' school of excellence with a boarding facility
12Project to support the creation of income-generating activities (AGR) and micro and small enterprises (MPE) for 500 young people in the Sud-Comoé Region
13Construction of phase 1 of the university town in Adiaké
14Construction and equipping of the Technical Centre for Applied Arts (CTAA) and support for graduates' access to employment
15Construction of a football sports-study centre with three (03) training stadiums and a small stand over 20 hectares
16Construction of a sports academy with a hotel and casino at N’Zi river lodge
17Construction of technical
and vocational high schools : 
• Construction of 04 introductory art schools (01 in each department of the PORO Region) 
• Construction of a tourism and hotel-management training centre
• Construction of a tourism and hotel-management training centre
18Establishment of a general mechanics and metalworking activity zone over 10 hectares (metalwork, automotive, motorcycles, aluminium, glazing and electrical work), including a training garage and a school specialising in solar energy, equipped with modern facilities, in SINEMATIALI
19Construction of private universities and higher education institutions
20Construction of a fire station in DIKODOUGOU and MBENGUE
21Construction of pre-schools and primary schools in every neighbourhood of the municipality of Maféré
22Establishment of a municipal library in Maféré
No.SECTORS : CONSTRUCTION / INFRASTRUCTURE
1Construction of the main bus station in Bouaké
2Construction of an interchange at the prefecture crossroads in Bouaké
3Construction of a flyover interchange
4Start of implementation of the sustainable urban mobility plan
5Construction of an EcoUniversCities city
6Construction of eight (08) modern embarkation and disembarkation jetties
7Construction of a cross-border bus terminal/parking facility in Noé (including a hotel and catering complex and storage areas)
8Paving of the Akressi - Abengourou road sections
9Paving of the Eboué-Etueboué-Akounougbé-Eboinda road sections
10Construction of a modern airport terminal (ahead of international flights)
11Urban redevelopment around the A3 motorway (following issuance of a DUP)
12Construction of an intercity and international bus station
13Paving of the pavements in the city of Bouaké
14Construction of 06 bus stations 
(03 in KORHOGO and 03 in the other
departments)
15Construction of a new bus station in Maféré
16Street lighting project for the outlying neighbourhoods of the municipality of Maféré
17Street paving project in the municipality of Maféré
No.SECTORS : TOURISM / HOUSING
1Construction of 5 000 social, mid-range and high-end housing units
2Development of a green leisure park over 40 hectares
3Construction of the Small-Scale Processing and Crafts Products Exhibition Centre (CEPTA)
4Development of Ehotilé Islands National Park for tourism purposes
5Construction of a hotel complex in a lush forest covering 10 to 15 hectares, comprising 25 fully self-contained duplex bungalows
6Preparation and implementation of the ecotourism development and management plan for the Soumié classified forest 
7Implementation of the development and management plan and socio-economic development of the Tanoé-Ehi Voluntary Nature Reserve
8Creation of tourist routes 
9Development of tourist areas in Tiapoom, Adiaké, Aboisso and Assinie
10Creation of a private rally circuit over an area of 5 hectares
11Construction and equipping of a regional museum
12Construction of 20 000 affordable, mid-range and high-end housing units
13Production and sale of serviced land reserves for housing construction
14Development of a 100-bed hotel / apartment facility for patients' companions
15Rehabilitation of craft villages in FAKAHA and NIONFOUIN
No.SECTORS : MINING / ENERGY / ENVIRONMENT
1Construction of a solar panel and equipment manufacturing plant (CÔTE D’IVOIRE SOLAIRE) with a capacity of 50 MW per year
2Establishment of a biofuel and fuel production unit using cashew shells, with a capacity of 13 500 tonnes per year
3Construction of a waste recovery and engineered landfill centre and a transfer centre to modernise and manage solid waste jointly across inter-municipal groupings
4Construction of a plant processing coconut waste into biochar, with a capacity of 1 440 tonnes per year
5Establishment of a charcoal and by-product production plant (using empty palm-kernel bunches and oil-palm trunks)
6Establishment of a medical and industrial waste storage and disposal unit with a capacity of 200 tonnes per year
7Restoration of mangroves and surrounding vegetation
8Construction sand extraction and marketing project
9Establishment of a plant processing palm and coconut shells into biomass and by-products
10Restoration of ecosystems adjoining the national sections of the Bia-Tanoé rivers over an area of 552 hectares
11Development of a phosphate deposit in Aboisso
12Additional development of the AFEMA gold mine
13Bottling and marketing of mineral spring water in krindjabo
14Establishment of biomass power plants in DIKODOUGOU
• Development of gasification plants using rice husks
15Establishment of a solid-waste treatment and conversion unit producing biomass in Maféré
16Construction of a water reservoir in Maféré
17Solar tricycle assembly project for passenger transport in Maféré
No.SECTORS : HEALTH / INDUSTRY
1Special pharmaceutical zone project
2Establishment of an electric motorcycle assembly plant
3Construction of an international clinic equipped with state-of-the-art technical facilities
4VITIB development project
5Construction of the modern N’DOTRE vehicle scrapyard
6Drip irrigation pipe manufacturing plant with a capacity of 32 400 000 metres per year
7Construction of an integrated knitwear manufacturing plant with a capacity of 20 tonnes per day
8Construction of a home-textile manufacturing plant with a capacity of 50 tonnes per day
9Greige fabric plant for African printing
10Denim fabric plant with a capacity of 19 tonnes per day and a capacity of 8,30 tonnes per day
11Ready-to-wear clothing plant with a capacity of 78 000 items per day
12Construction of a self-contained knitted-fabric manufacturing plant with a capacity of 12 tonnes per day
13Takeover of the Gonfreville textile plant (from spinning to garment making) over 60 Ha
14Establishment of a jute production plant (bags for packaging agricultural products)

Source : CNP-PPP

 

Investment trends from 2019 to 2023 (in billions of FCFA)

Categories

2019

2020

2021

2022

2023

Public

1 734,8

1 962,0

2 293,2

3 140,3

3 257,2

Private

6 111,1

5 418,7

6 206,9

7 886,7

8 984,7

Source : MEPD/DGE

Investment programming trends from 2024 to 2029 (in billions of FCFA)

 

2024

2025

2026

2027

2028

2029

Public

3 692,3

3 879,1

4 395,9

4 932,2

5 365,1

5 852,3

Private

10 048,7

11 406,5

12 863,2

14 724,5

16 617,2

18 582,5

Source : MEPD/DGE

Volume of approved investments from 2012 to 2023 

Source : CEPICI 

Breakdown of approved FDI by sector of activity in 2023 (in billions of FCFA) 

Sector of activity 

FDI amount 

Percentage 

AGRI-FOOD / AGRO-INDUSTRY 

148 039 039 381 

29,20 

CHEMICAL INDUSTRY (COSMETICS - PHARMACEUTICALS - RUBBER) 

74 541 036 904 

14,70 

CONSTRUCTION INDUSTRY 

71 756 949 510 

14,15 

TRANSPORT / STORAGE (HANDLING) 

67 710 517 031 

13,35 

TELECOMMUNICATIONS 

56 934 683 639 

11,23 

OTHER MANUFACTURING INDUSTRIES 

50 109 237 115 

9,88 

ENERGY (GAS - WATER) 

16 047 696 298 

3,16 

EXTRACTIVE INDUSTRY 

11 446 300 577 

2,26 

OTHER SERVICES 

5 195 164 233 

1,02 

HOTELS (FOOD SERVICE - ACCOMMODATION) 

4 744 631 242 

0,94 

EDUCATION / TRAINING / HEALTH 

925 371 194 

0,18 

FOOD-CROP FARMING, LIVESTOCK 

-411 307 602 

-0,08 

Grand total 

507 039 319 522 

100 

Source: CEPICI 

  

Breakdown of approved FDI by sector of activity in 2023 

Statistics

Source : CEPICI 

Ten (10) main foreign investor countries in 2023 

Statistics

 Source CEPICI 

Main foreign investors in 2023 

RANK 

ORIGIN 

AMOUNT

INVESTMENTS 
(in billions of FCFA)

1 

Burkina Faso 

112 926 127 808 

2 

Turkey 

66 175 424 172 

3 

China 

49 976 666 144 

4 

France 

49 206 480 601 

5 

Togo 

48 296 684 599 

6 

Mauritius 

29 861 709 612 

7 

Morocco 

18 337 971 107 

8 

British Virgin Islands 

15 600 000 000 

9 

Senegal 

14 029 748 730 

10 

Lebanon 

12 383 317 016 

11 

Hong Kong 

11 906 717 205 

12 

Mali 

11 111 222 510 

13 

United Arab Emirates 

10 724 284 839 

14 

Cyprus 

9 214 430 975 

15 

England 

7 289 075 166 

16 

Switzerland 

4 590 600 513 

17 

Panama 

4 394 853 076 

18 

Netherlands 

4 144 919 105 

19 

Singapore 

3 307 735 958 

20 

Tunisia 

3 034 566 643 

21 

Cameroon 

2 877 534 007 

22 

Belgium 

2 374 459 910 

23 

Niger 

2 324 232 187 

24 

Luxembourg 

2 302 451 511 

25 

Cayman Islands 

2 022 000 709 

26 

India 

1 878 125 609 

27 

Spain 

1 578 540 185 

28 

Ghana 

1 283 860 730 

29 

Malaysia 

806 066 162 

30 

Italy 

595 848 649 

31 

Benin 

518 836 743 

32 

USA 

498 278 438 

33 

Portugal 

497 327 549 

34 

Germany 

292 914 315 

35 

Canada 

272 057 568 

36 

Nigeria 

168 009 074 

37 

Monaco 

143 985 835 

38 

Ukraine 

51 270 000 

39 

Sudan 

40 984 566 

Grand total 

507 039 319 522 

Source : CEPICI 

One-Stop Shop for Business Formalities (GUFE) 

Item 

2022 

2023 

Change 

Number of applications submitted 

23 229 

25 422

 9,4%

Number of companies created 

23 940 

26 117 

9% 

Projected number of jobs

6 273 

5 207 

-17% 

Average number of companies created per day 

95 

101 

6% 

Average time to set up a company, in days 

3,4 days 

5,2 days 

- 

Source : CEPICI 

 

Project catalogue

No.

SECTOR : AGRO-INDUSTRY

1

Industrial irrigated maize plantation covering 600 Ha

2

Industrial chilli pepper plantation covering 50 Ha

3

Industrial plantain plantation covering 100 Ha

4

Industrial pineapple production over 2000 Ha

5

Construction of a cashew nut processing plant with a capacity of 15 000 tonnes per year

6

Natural rubber plant processing latex with a capacity of 70 000 tonnes per year

7

Shea nut processing plant with a capacity of 1000 tonnes per year

8

Construction of a mango and vegetable drying plant (4 000 tonnes of vegetables and 3 000 tonnes of dried mangoes per year) – 2PAI-NORD (CI)

9

Construction of a peanut oil and paste plant producing 5 800 tonnes of products per year (1 500 tonnes of oil and 4 300 tonnes of peanut paste per year) – 2PAI-NORD (CI)

10

Construction of a plant producing cottonseed oil and animal feed (3 800 tonnes of oil and 10 700 tonnes of animal feed per year) – 2PAI-NORD (CI)

 11

Construction of a meat production plant with a capacity of 13 300 tonnes per year – 2PAI-NORD (CI)

12

Construction of a mango and cashew apple juice plant (90 000 tonnes of fresh mangoes and 800 000 tonnes of cashew apples processed per year) - 2PAI-NORD (CI)

13

Construction of a plant producing oil from shea butter (1 000 tonnes per year) – 2PAI-NORD (CI)

14

Construction of a maize flour plant with a capacity of 90 000 tonnes per year – 2PAI-NORD (CI)

15

Construction of a packaging plant for fresh market-garden produce (54 000 tonnes of fresh vegetables per year) – 2PAI-NORD (CI)

16

Frozen plantain and yam chips production unit with a capacity of 10 000 tonnes per year

17

Fruit and vegetable processing unit producing jam, cosmetic products and spices, with a capacity of 18 000 tonnes per year

18

Construction of 15 independent cassava processing units, each with a capacity of 25 tonnes per day

19

Cassava processing unit with a capacity of 1,5 tonne per day

20

Cassava plantation combined with a cassava-to-starch processing plant with a capacity of 12 tonnes per hour

21

Okra processing unit with a capacity of 1 tonne per day

22

Value addition to products in the cocoa value chain by « Maison Mandjou ».

23

Establishment of a 6000 Ha rice-growing complex in central Côte d’Ivoire 

24

Development of rice-growing complexes in the Agneby-Tiassa Region

25

Establishment of a unit to process raw cocoa beans into finished and semi-finished products (cocoa liquor, cocoa powder, cake and cocoa butter), with a capacity of 30 000 tonnes per year

26

Industrial maize plantation covering 100 Ha

27

Establishment of an integrated agro-industrial pineapple production and processing unit over 250 hectares

28

Establishment of an integrated agro-industrial rice production and processing unit

29

Establishment of a unit producing refined oil (olein), stearin and fatty acids (olein/cooking oil: 80 000 t / year, fatty acids: 5 000 t / year; stearin: 20 000 t / year)

30

Establishment of a unit producing oil, meal and shells from palm kernels (palm kernel oil / year: 4 000 t / year; meal: 5 000 t / year; palm kernel shells: 12 000 t / year)

31

Establishment of a cocoa bean processing unit producing cocoa mass, with a capacity of 3 000 tonnes per year (for cooperatives)

32

Establishment of a palm fruit processing unit producing red palm oil, with a capacity of 32 400 tonnes per year

33

Establishment of a TSR10-type rubber production plant with a capacity of 12 500 tonnes per year

34

Establishment of a natural rubber plant processing latex with a capacity of 33 000 tonnes per year

35

Establishment of modern food-crop storage and drying units

36

Establishment of three (03) cassava-to-starch flour processing units for the agri-food industry, each with a capacity of 3 000 tonnes per year

37

Establishment of a palm oil production unit with a capacity of 6 000 tonnes per year

38

Establishment of a modern agro-industrial processing unit for cereals, food crops, tubers and oilseeds, with a capacity of 10 000 tonnes per year 

39

Project to take over a semi-industrial unit producing and marketing attiéké and by-products (4,5 tonnes of attiéké /month, 1 tonne of starch, 1 tonne of cassava peel for livestock feed)

40

Establishment of a small-scale organic fertiliser plant using cocoa residues, with a capacity of 1 500 tonnes per year

41

Establishment of an industrial coconut plantation and processing into by-products

42

Establishment of a local coffee processing unit (to be certified) 

43

Establishment of an industrial plantation of premium local pepper (to be certified)

44

Establishment of an industrial food-crop and fruit plantation (papaya, passion fruit, mangosteen, etc.)

45

Project to take over the industrial dessert banana plantation (former CANAVESE) in Akressi

46

Establishment of a maize and cassava processing unit in Aboisso 

47

Establishment of small-scale cashew processing units

48

Development and rehabilitation of irrigated food-crop areas in NAFOUN and DIKODOUGOU

49

Establishment of a two-hectare greenhouse market-gardening plantation in Maféré

50

Establishment of a four-hectare irrigated plantain plantation in Maféré

51

Industrial production of Maféré Bread

 

No.

SECTOR : LIVESTOCK

1

Establishment of a poultry farm with 1,2 million birds

2

Construction of a modern poultry slaughterhouse with a capacity of 50 000 birds per day

3

Development of an integrated cattle ranching project, including a vocational training centre and a fodder production unit (three ranches to fatten 3 000 animals over 1 500 ha)

4

Construction of a livestock feed plant using rice bran, mango peel and cashew apple peel (340 000 tonnes of livestock feed per year) – 2PAI-NORD (CI)

5

TAABO fisheries park covering 76 Ha

6

Fish farming in floating cages with a capacity of 20 000 m3

7

Fish feed production plant with a capacity of 2000 tonnes per year

8

10 modern fish-drying ovens with a capacity of 100 tonnes per day

9

Integrated poultry hub covering 16 Ha

10

Hatcheries for day-old chicks, with a capacity of 2 300 000 day-old chicks per year

11

Pig farm with a capacity of 236 000 Kg per year

12

Integrated pig production project

13

Organic pig feed production plant with a capacity of 800 tonnes per year

14

Construction of a poultry complex to produce poultry and by-products (protein meal)

15

Construction of a fisheries production and processing complex in Grand Bassam

16

Establishment of a poultry feed production unit with a capacity of 5 000 tonnes per year

17

Establishment and operation of a fish farm covering 25 hectares

18

Establishment and operation of a marine fishing unit producing 720 tonnes of fish per year

19

Establishment of a day-old chick production unit with a capacity of 12 000 000 chicks per year

20

Shrimp farming project with annual production of 1200 T

21

Aquaculture industry modernisation project on Lake Ayamé

22

Fish farming development project (Emeraude Pisciculture Sud Comoé farm): production of 10 tonnes of fresh tilapia per year

23

Installation of livestock feed (fodder) production units: 5 000 tonnes per year

24

Establishment of a fish farm in LOKOLI

25

Support for young people to take up beekeeping and honey production for export in the LOKOLI area

26

Construction of a modern abattoir in Maféré

 

No.

SECTORS : LOGISTICS / TRADE

1

Development of a logistics platform in the 1000-hectare industrial zone in Bouaké

2

Installation of a cold chain with a containerised central refrigeration system

3

Construction of the Bouaké wholesale market over 12,4 Ha

4

Construction of a space for 200 restaurants / refreshment stands

5

Establishment of cold-storage and ripening warehouses (cold chain, particularly for storing mangoes, with a cooling capacity of 80 000 tonnes per year) in KORHOGO

6

Establishment of an agro-industrial, commercial and logistics platform (PK 108)

7

Construction of terminals and logistics platforms

8

Construction of a wholesale market

9

Construction of a modern market with a modern shopping centre.

10

Establishment and development of industrial zones in Adiaké and Tiapoum

11

Construction of themed markets (timber, hardware, mechanics, fisheries products)

12

Expansion of the industrial activity zone park in KORHOGO

 

No.

SECTORS : SERVICES / EDUCATION

1

Listening and telephone call centre

2

Primary and secondary school construction project

3

Opening of an international high school (French or American)

4

Construction of a municipal plant nursery in Bouaké

5

Construction of a cinema and performance venue in Bouaké

6

Establishment of a sanitation brigade

7

Rehabilitation of the Bouaké municipal swimming pool

8

Modernisation of the Waraniéné craft centre

9

Construction of an agricultural training centre

10

Construction of a vocational high school in the fields of fishing, mining, construction, solar energy, etc. in the region

11

Construction and equipping of a girls' school of excellence with a boarding facility

12

Project to support the creation of income-generating activities (AGR) and micro and small enterprises (MPE) for 500 young people in the Sud-Comoé Region

13

Construction of phase 1 of the university town in Adiaké

14

Construction and equipping of the Technical Centre for Applied Arts (CTAA) and support for graduates' access to employment

15

Construction of a football sports-study centre with three (03) training stadiums and a small stand over 20 hectares

16

Construction of a sports academy with a hotel and casino at N’Zi river lodge

17

Construction of technical
and vocational high schools : 
• Construction of 04 introductory art schools (01 in each department of the PORO Region) 
• Construction of a tourism and hotel-management training centre
• Construction of a tourism and hotel-management training centre

18

Establishment of a general mechanics and metalworking activity zone over 10 hectares (metalwork, automotive, motorcycles, aluminium, glazing and electrical work), including a training garage and a school specialising in solar energy, equipped with modern facilities, in SINEMATIALI

19

Construction of private universities and higher education institutions

20

Construction of a fire station in DIKODOUGOU and MBENGUE

21

Construction of pre-schools and primary schools in every neighbourhood of the municipality of Maféré

22

Establishment of a municipal library in Maféré

 

No.

SECTORS : CONSTRUCTION / INFRASTRUCTURE

1

Construction of the main bus station in Bouaké

2

Construction of an interchange at the prefecture crossroads in Bouaké

3

Construction of a flyover interchange

4

Start of implementation of the sustainable urban mobility plan

5

Construction of an EcoUniversCities city

6

Construction of eight (08) modern embarkation and disembarkation jetties

7

Construction of a cross-border bus terminal/parking facility in Noé (including a hotel and catering complex and storage areas)

8

Paving of the Akressi - Abengourou road sections

9

Paving of the Eboué-Etueboué-Akounougbé-Eboinda road sections

10

Construction of a modern airport terminal (ahead of international flights)

11

Urban redevelopment around the A3 motorway (following issuance of a DUP)

12

Construction of an intercity and international bus station

13

Paving of the pavements in the city of Bouaké

14

Construction of 06 bus stations 
(03 in KORHOGO and 03 in the other
departments)

15

Construction of a new bus station in Maféré

16

Street lighting project for the outlying neighbourhoods of the municipality of Maféré

17

Street paving project in the municipality of Maféré

 

No.

SECTORS : TOURISM / HOUSING

1

Construction of 5 000 social, mid-range and high-end housing units

2

Development of a green leisure park over 40 hectares

3

Construction of the Small-Scale Processing and Crafts Products Exhibition Centre (CEPTA)

4

Development of Ehotilé Islands National Park for tourism purposes

5

Construction of a hotel complex in a lush forest covering 10 to 15 hectares, comprising 25 fully self-contained duplex bungalows

6

Preparation and implementation of the ecotourism development and management plan for the Soumié classified forest 

7

Implementation of the development and management plan and socio-economic development of the Tanoé-Ehi Voluntary Nature Reserve

8

Creation of tourist routes 

9

Development of tourist areas in Tiapoom, Adiaké, Aboisso and Assinie

10

Creation of a private rally circuit over an area of 5 hectares

11

Construction and equipping of a regional museum

12

Construction of 20 000 affordable, mid-range and high-end housing units

13

Production and sale of serviced land reserves for housing construction

14

Development of a 100-bed hotel / apartment facility for patients' companions

15

Rehabilitation of craft villages in FAKAHA and NIONFOUIN

 

No.

SECTORS : MINING / ENERGY / ENVIRONMENT

1

Construction of a solar panel and equipment manufacturing plant (CÔTE D’IVOIRE SOLAIRE) with a capacity of 50 MW per year

2

Establishment of a biofuel and fuel production unit using cashew shells, with a capacity of 13 500 tonnes per year

3

Construction of a waste recovery and engineered landfill centre and a transfer centre to modernise and manage solid waste jointly across inter-municipal groupings

4

Construction of a plant processing coconut waste into biochar, with a capacity of 1 440 tonnes per year

5

Establishment of a charcoal and by-product production plant (using empty palm-kernel bunches and oil-palm trunks)

6

Establishment of a medical and industrial waste storage and disposal unit with a capacity of 200 tonnes per year

7

Restoration of mangroves and surrounding vegetation

8

Construction sand extraction and marketing project

9

Establishment of a plant processing palm and coconut shells into biomass and by-products

10

Restoration of ecosystems adjoining the national sections of the Bia-Tanoé rivers over an area of 552 hectares

11

Development of a phosphate deposit in Aboisso

12

Additional development of the AFEMA gold mine

13

Bottling and marketing of mineral spring water in krindjabo

14

Establishment of biomass power plants in DIKODOUGOU
• Development of gasification plants using rice husks

15

Establishment of a solid-waste treatment and conversion unit producing biomass in Maféré

16

Construction of a water reservoir in Maféré

17

Solar tricycle assembly project for passenger transport in Maféré

 

No.

SECTORS : HEALTH / INDUSTRY

1

Special pharmaceutical zone project

2

Establishment of an electric motorcycle assembly plant

3

Construction of an international clinic equipped with state-of-the-art technical facilities

4

VITIB development project

5

Construction of the modern N’DOTRE vehicle scrapyard

6

Drip irrigation pipe manufacturing plant with a capacity of 32 400 000 metres per year

7

Construction of an integrated knitwear manufacturing plant with a capacity of 20 tonnes per day

8

Construction of a home-textile manufacturing plant with a capacity of 50 tonnes per day

9

Greige fabric plant for African printing

10

Denim fabric plant with a capacity of 19 tonnes per day and a capacity of 8,30 tonnes per day

11

Ready-to-wear clothing plant with a capacity of 78 000 items per day

12

Construction of a self-contained knitted-fabric manufacturing plant with a capacity of 12 tonnes per day

13

Takeover of the Gonfreville textile plant (from spinning to garment making) over 60 Ha

14

Establishment of a jute production plant (bags for packaging agricultural products)

Source : CNP-PPP